Data Centers in Colorado Springs

Colorado Springs is considering options for data center approval standards and ongoing regulation. The national discourse is developing rapidly, but evidence on how different regulatory frameworks perform remains limited. This report examines the processes and regulatory structures the City has in place, the approaches taken by comparable municipalities, the conclusions the existing evidence supports, and the policy options available.

Key Findings
Colorado Springs is in a unique position. It owns major utilities including electrical, natural gas, water, and wastewater services. [1] The City Council acts as the Utilities Board and can set prices and terms of service without approval from the state’s Public Utilities Commission, allowing the City to address issues that other cities can reach only through zoning.
The Electric Large Load safeguards do not apply to existing data centers whose load is below the tariff threshold. Restrictions regarding Electric Large Load apply only to those plants with actual or reasonably expected demand of 10 megawatts or more. [2] Four of the largest data centers in the City have reported loads of 1, 4, 5 and 6 megawatts each. [3]
The zoning code does not classify data centers as a separate land use category. The City’s Unified Development Code (UDC) classifies them as “Light Industry,” a permissive category that also includes commercial bakeries, print shops, and electronics manufacturing. The UDC includes two data-center-specific requirements, governing landscaping and parking. [4]
Data on current water usage provides a foundation for regulation. The four biggest data centers in the City use about 11,000 gallons per day for each megawatt of electric load, at a rate that holds fairly evenly across the four sites. [5] Collectively they use about 177,000 gallons per day, equal to about 0.3 percent of average system-wide use and the annual equivalent of about 996 households.
The City has enforceable noise codes, but they could be refined and broadened. Levels are set by zone and hour, with the most stringent limit applying to sources measurable from multiple zones. [6] The City applies the limit corresponding to the adjacent use, so facilities next to residential areas face a 55 dB(A) daytime and 50 dB(A) nighttime limit. [7] Measurement is A-weighted, which may not fully account for low frequencies. [8]
The most commonly cited judicial reversal turned on process, not substance. In Board of County Supervisors of Prince William County v. Oak Valley Homeowners Association (March 31, 2026), the Virginia Court of Appeals invalidated three rezoning ordinances for failure to comply with notice requirements under both statutory and local law. The County discontinued its appeal after litigation expenses exceeded $1.7 million. [9]
The City can pursue community investment under several legal authorities. Land use conditions, development agreements, and utility-service terms have different legal limits. Uniformity alone does not authorize every requirement, including local hiring and investment obligations. [10]
Peer jurisdictions offer examples, but not evidence of success. We did not locate published information evaluating whether new regulations achieved their policy objectives.

Recommendations
The Proposed Policy Options section of the report identifies fourteen policy alternatives for the City to consider. Here we briefly summarize and emphasize the key themes of those where there is the strongest precedent and confidence.
Define data centers. Creating a unique classification in the UDC provides the clearest pathway to effective regulation of center approval and oversight. As a component of this, the City could define the threshold(s) above which sites generate enhanced safeguards for mitigating adverse impacts. In conjunction with this, the City might compile and publish an inventory of existing data center sites and could report impacts on an aggregated basis.
Clarify and codify related standards. Noise regulations, water study triggers, and methods for modifying existing uses already exist in City policy. Identifying gaps and updating policies to address this rapid-growth area is more readily adoptable than wholly new initiatives.
Establish a clear, transparent process for approval. Because of their current classification, data center applications do not trigger a public hearing. Establishing a clear and transparent process for center consideration and ongoing oversight, perhaps for sites exceeding certain parameters, could ameliorate public concerns.
Adopt broadly applicable community investment requirements. Adopting initial requirements by ordinance, applying them uniformly, and negotiating anything beyond them through a site-specific agreement based on its unique characteristics offers a broad and sustainable path to securing community investment.

OCTOBER | 2026

Executive Summary

Introduction

The debate regarding data center proliferation has captured national attention. The facilities can be large, and their ongoing operation requires dedicated energy and water. Construction creates jobs, though ongoing employment impacts vary. In many cases, new data centers have been approved under preexisting regulatory schemes that were not designed for that purpose and do not necessarily require public input.

Because it owns its own electrical, natural gas, water, and wastewater utilities, Colorado Springs is in a unique position to create a comprehensive regulatory regime.

Purpose. The purpose of this report is to provide objective, evidence-based data and analysis to city leadership to support its consideration of new data center projects and their ongoing regulation.

Scope of Baseline Data. In order to generate a landscape assessment of the City’s regulation of data centers and public concerns that have been expressed, the report references permitting documents; sound studies; electricity, water, and other utility rates; and additional materials provided by the City.

Evidence Supporting Findings. For identifying and assessing its core findings and recommendations, the report examines an array of ordinances, judicial opinions, administrative and legislative records, as well as secondary sources to supplement these primary materials.  

Terminology. This report uses “community investment” to describe the commitments the City secures from data center developers, often called public benefits or community benefits elsewhere.

Current City Landscape

Utility Ownership and Oversight
Colorado Springs is a home rule city. [11] Through Colorado Springs Utilities (CSU), it owns four core public utilities that cannot be sold or leased without a supermajority vote of City residents. [12] The City Council serves as the board of CSU and has authority to set rates for the services it provides. [13] Unlike most of the City’s peers, that means that these retail rates are not governed by the Colorado Public Utilities Commission (PUC). [14]
This gives the City the ability to act on data center-related issues with unique speed and precision. Denver, by way of comparison, can only advocate with the state regarding utility rates. [15] Likewise, Aurora recognized that it lacks the ability to directly address the energy-related impacts of the data center regulations it is considering. [16] The extensive burden of Xcel Energy’s proposed tariff on large-load sites, which includes fifteen-year service agreements, deposits, fees for conducting studies, and shifting of cost burden entirely at loads of 50 MW or more, must be approved by the state PUC and was pending as of August 2026. [17]
City Data Centers
CSU has publicly identified seven data centers with a load exceeding one megawatt. [18] This chart captures more recent City-provided data that affords a detailed look at the largest sites:
Customer Electric load (MW) Water use (gallons per day) Water use (gallons per year) Acre-feet per year Household equivalent
Customer 1 5 54,254 19,802,710 61 306
Customer 2 1 9,251 3,376,615 10 52
Customer 3 4 46,123 16,834,895 52 260
Customer 4 6 66,892 24,415,580 75 378
Total 16 176,520 64,429,800 198 996
These four centers use water per unit of electric load with remarkable consistency. Their usage ranges from 9,251 to 11,531 gallons per day per megawatt, which yields a weighted average of approximately 11,000 gallons/day/megawatt. This provides a strong evidence basis for predicting likely water usage of future data centers. For example, a large facility with a load of 20 megawatts, assuming comparable design features, could fairly be expected to consume 220,000 gallons of water per day, which is equal to the standard consumption of about 1,240 homes. Because the rate reflects the heat-rejection systems installed at these four sites, it should not be applied to a facility proposing closed-loop liquid cooling, which uses materially less water.
For context, the total consumption across these four sites is relatively modest. The 176,500 gallons they consume per day is approximately 0.3 percent of average systemwide use (60 million gallons per day). [19] CSU has stated that City data centers currently account for less than 0.05 percent of total City-wide consumption, so these figures could be reconciled as the dialogue on these issues continues. 
With 10 megawatts serving as the large-load standard, the existing loads reported to the Romer Institute fall below that threshold. Therefore, the existing protections relating to sites that meet it, such as a ten-year term, collateral, assumption of infrastructure costs, and other requirements, do not apply.
Our research was not able to produce a comprehensive City data center inventory. Because there is no unique classification for these sites, they are usually permitted by right so long as they comply with otherwise applicable standards and therefore do not typically require a public hearing. Additional transparency regarding the data center footprint and ongoing approval may address some of the public concern regarding this trend.
Current Process for Data Center Approval
The Unified Development Code (UDC) provides for approximately 140 different categories of use, but “data center” is not included among them. By code, these sites fall under the “Light Industry” designation that is permitted in areas zoned as business parks. [20] The stated purpose of that zone contemplates uses whose operations are “quiet and clean.” [21] UDC regulations apply to data centers in two ways: those adjoining single-family or two-family residential property must meet Buffer 2 landscape and screening standards; and parking is set at one space per 1,000 square feet of gross floor area.
Approval of sites that fall into this category of use is administrative in nature. For example, approval of a relatively large (442,468-square-foot) facility was accomplished in June 2026 via modification to the applicable development plan. [22] Public notice was provided via postcards, emails, signs, and two meetings managed by the applicants and the City received approximately 1,500 public comments as of that staff report, a count the City reports continued to rise afterward. [23]
The pathway for considering a new data center site varies across the City, because it is tied to zoning structures that differ by district. For example, a data center in an Airport Planned Development zone was unanimously authorized by a use variance. [24]
With regard to the potential to apply new regulation to already-approved sites, City Code 7.5.515 states that approval of a Development Plan is a planning document. It does not grant a variance and expires six years after approval unless a building permit is issued or a use shown on the plan commences, with possible two-year extensions. [25] Additional considerations relating to existing sites are taken up further below.
Existing Safeguards
Electric Load. The city adopted protections for large-load industrial service, effective January 2026. These measures apply to CSU customers whose electricity demand equals or exceeds, or is reasonably expected to equal or exceed, 10 MW. Its terms include:
  • A 10-year minimum contract;
  • Monthly minimum charges equal to the higher of what the site actually used or the full contracted load amount for 10 years, regardless of actual electricity use;
  • 36 months of collateral;
  • Customer coverage of costs relating to transmission and extended distribution;
  • As well as other charges. [26]
These requirements are intended to prevent these sites from shifting costs to existing customers and hedge against the risk the site will be abandoned. [27] Project-specific contracts may include additional terms not addressed in this standard schedule, which is technology-neutral. [28]
Water. Site-specific, large, nonresidential water use is available from CSU on a contractual basis. [29] Charges increase with consumption, but non-potable water has a separate, lower rate, which is an incentive for sites to access reclaimed water. [30]
A CSU publication requires data centers requesting at least 250,000 gallons of water per day to participate in a study that could precipitate imposition of a closed-loop system. That study evaluates available supply, system capacity, delivery facilities, and any agreements needed before water capacity is reserved. [31] Using the 11,000 gallons/MW/day standardized rate described above, only facilities exceeding approximately 23 MW would be subject to that policy, a level far above any of the current facilities.
Interwoven with concerns about data center water usage is the ongoing statewide drought. CSU initiated a Water Shortage Preparation process in March. In June, it reported that projected annual water yield will be the lowest ever recorded at 41 percent of the average. [32]
Noise. City limitations on noise are dictated by the classification of adjacent property use and time of day: [33]
Zone 7:00 a.m. – 7:00 p.m. 7:00 p.m. – 7:00 a.m.
Residential 55 dB(A) 50 dB(A)
Commercial 60 dB(A) 55 dB(A)
Light industrial 70 dB(A) 65 dB(A)
Industrial 80 dB(A) 75 dB(A)
If a source of noise registers in more than one zone, the one with the lower cap applies. Any facility that neighbors a residential area is therefore subject to the lowest noise threshold. [34] This applies regardless of the zoning designation of the emitting property.
The City uses an A-weighted approach to measuring volume, which may not fully account for steady, low-frequency sounds. Between 7 a.m. and 7 p.m., for up to fifteen minutes in any given hour, allowance is made for up to 10 dB(A) of additional volume. [35] The volume caps in the table above are reduced by 5 dB(A) for pulsing or repetitive sounds. [36] Hardship waiver permits are available at the Mayor’s discretion. [37]
Adopted policy direction. In August 2026, the City issued Community-First Data Center Standards, [38] which set the following commitments for new data center projects:
  1. Pay the full cost of substantial infrastructure upgrades
  2. Pay for reserved power capacity even if it is not used;
  3. Protect the City’s long-term water supply;
  4. Address and mitigate noise and other neighborhood disruptions;
  5. Comply with all existing City environmental and development rules; and
  6. Create sustained value for the community and conduct public hearings to collect input.
These policies are directional rather than constituting an enforceable ordinance or Code amendment.
Community Concerns
Commonly expressed areas of concern regarding data centers include noise levels, electricity demand and impact on consumer costs, water use, transparency regarding center approval, and air quality. A recurring theme relating to the approval process is that a clear standard for approval be established and applied on a consistent basis, rather than generated ad hoc for each new site proposal. The City Planning Commission held a public appeal hearing on July 23, 2026. No separate City-convened forum on citywide data center policy was located; earlier community sessions were organized by residents or the applicant. [39]

Comparable Municipalities

Criteria
In identifying municipalities with track records that produce evidence that may be relevant to the Colorado Springs context, we considered whether they had adopted new policies in response to the data center trend, and whether they were comparable to the City in terms of population, home rule status, and ownership of utilities.
In conducting this survey, we found that most localities with more thorough regulatory regimes did not own their utilities to a degree similar to the City, which may be partly why they put new policies into zoning rules or other local code modifications. For those, the framing of these new regulations may be informative but their process for adoption likely is not.
Colorado Jurisdictions
Jurisdiction Utility Instrument Substance
Longmont Municipal electric Ordinance O-2026-34, June 2026 Prohibits facilities at or above 100 MW; caps others at the lower of 100 MW or 5% of regional grid capacity; confines smaller facilities to one district with specific water, cooling, efficiency, noise and lighting standards [47]
Weld County Investor-owned Ordinance 2026-01, effective April 2026 Permanent operating standards including a 65 dB(C) limit at the property boundary [48]
Denver Investor-owned Council Bill 26-0431, May 2026 Temporary moratorium; ratepayer protections are not binding [49]
Jefferson, Boulder, Larimer Counties Investor-owned Moratoriums, 2026 Temporary moratoria while standards are developed [50] [50B] [50C] [50D]
Aurora Investor-owned None adopted Council advised it lacked authority over energy impacts [51]
Adams, Arapahoe, Douglas, Mesa, Pueblo Counties Mixed None adopted No data center standards located; Douglas County approved a 35-year rebate of its share of business personal property tax for a Parker data center in August 2026 [52] [52B]

Longmont is the closest Colorado analog regarding utility structure, because it also is served by a municipally-owned electrical service provider. As the chart above indicates, it has elected to place a hard cap on data center energy demand and additional restrictions that are consistently applied across cases. Weld County has the only C-weighted, data center-focused noise constraint we found, with the 65 dB(C) limit that is assessed at the facility property boundary.

Summary of Out-of-State Peers
Jurisdiction Utility Instrument Substance
Nashville–Davidson County, TN Municipal Executive Order 59 (June 2026); Ordinance BL2026-1391; Ordinance BL2026-1448 EO 59 directed departments to assess infrastructure, environmental, residential and economic impacts; BL2026-1391 enacted zoning categories and the 20,000 sq ft / 5 MW boundary; BL2026-1448 established a temporary moratorium [53]
Birmingham, AL Investor-owned ZAC2026-00001, June 2026 Conditioned on a permitted use; limits routine on-site power to solar or fuel cells and prohibits gas turbines and 24/7 diesel generation, allowing fossil-fuel units only for emergency and testing use; classifies sites by design and function [54]
Chandler, AZ Investor-owned Ordinance No. 5033 Ambient-baseline sound standard evaluated by independent pre-approval study and annual studies for five years, instead of a fixed volume cap [55]
Phoenix, AZ Investor-owned Ordinance G-7396, July 2025 Special permitting established in five districts; 55/45 dB(A) day/night cap set at residential property lines; 150-foot mechanical setback [56]
Mesa, AZ Municipal (partial) Zoning amendments, 2025 Resource use standards including water reporting [57] [57B]
El Paso, TX Investor-owned Policy framework, July 2026 Framework adopted; implementing ordinance not enacted, so facilities remain permitted by existing code (not data center-specific) standards [58]
Cheyenne, WY Mixed None adopted Proposed moratorium failed [59] [59B]

Chandler’s approach to noise regulation is an interesting example because it does not set a fixed numeric decibel limit that applies to all potential facilities. The applicant is required to measure the existing ambient noise at the site before their proposal is approved, proffer evidence that their facility will not exceed that level, and test noise levels against that site-specific standard once per year for five years. It is the only data center-specific instance of this approach we identified, and it is offered as a case study rather than a recommendation.

Birmingham offers a helpful example of using standardized terminology for classifying sites based on their design specifications and functionality rather than entertaining the variable ways in which applicants might define their proposed sites. That city also evaluates the proposal based on projected characteristics once it is fully built out and mandates new review when there is a material change to the site plan. Nashville considered and adopted separate provisions to create its regulatory regime, rather than trying to regulate the space in one omnibus vehicle.

Cautionary Anecdotes
Prince William County, Virginia. In March 2026 the Virginia Court of Appeals upheld a lower court decision striking down three rezoning ordinances that covered 37 data centers because their approval did not comply with public notice-and-comment requirements. With closer inspection, some of these lapses appeared to be technical and likely could have been avoided: a newspaper advertisement did not run because the county did not confirm its publication; alternative notices were not given for the required time; and the text of the ordinance was not posted until five days before the review hearing. The court held that even though there was notice given, it did not strictly comply with the detailed requirements under law. Prince William County dropped its appeal and the developer withdrew its remaining appeal, potentially due to the cited $1.7 million in litigation costs the ordeal had already accumulated.
Tucson and Pima County, Arizona. After Tucson declined to annex a proposed facility site and the affiliated water service, the developer relocated to the unincorporated county and relied on air cooling and private wells. [60] [60B] [60C] This case demonstrates the authority of a city to regulate data centers and the limitations of local control.
Imperial County, California.  This example demonstrates the importance of identifying and validating sources of water use before new sites are approved. There, an applicant had committed to use recycled wastewater for facility cooling. When two attempts to arrange recycled-water service failed, it sued the local irrigation district to get access to Colorado River water. [61]
Peculiar, Missouri. The city made data centers a by-right use by inserting a definition into its light-industrial zoning, then later deleted the definition in October 2024. Listing a use as permitted by right forecloses case-by-case review, while requiring a conditional use permit preserves it. [62]
Phoenix, Arizona (noted in prior section). Existing property owners filed claims against Phoenix after it adopted its special permit ordinance under Arizona’s Proposition 207, which allows compensation when land use regulation diminishes property value. Properties whose use requires a special permit are less valuable than property that permits use by right. Rather than pay for the difference in value, the city decided to grant waivers of the new requirement in some cases. [63]
Limitations on Drawing Comparison with other Jurisdictions
No jurisdiction we reviewed had published an evaluation of the performance of its data center regulatory regime. Chandler’s annual sound studies are an example of a future source of data that could be tracked. All other case studies speak to means and content of policy rather than bona fide results.

Potential Decision Criteria and Oversight

Criteria for Energy Consumption
Localities that vary regulatory standards for different sites usually distinguish them by energy load. They sometimes also consider square footage and water use. As referenced above, CSU currently distinguishes 10 MW sites and applies a large load rate schedule to them.
Particularly because none of its sites currently exceed this threshold, the City has essentially a clean slate for determining the tiers it might apply to different categories of data centers. If it chooses to do so by a land use designation, that need not correspond directly to the existing ratemaking threshold, though it would still apply to energy rates unless the City were to issue an Economic Development Special Contract.
While the City does not currently categorize industrial uses by the size of the facility, it does do so in other contexts, such as for day care centers, so there is precedent in the City’s regulatory practices for distinguishing data centers this way if it chooses to do so.
Noise
Measurement. The City code currently evaluates noise volume with A-weighting, which estimates how human ears respond to quiet sounds but discounts lower frequencies by roughly 39 decibels at 31.5 hertz. [64] It therefore does not fully account for the “deep hum” that is often associated with data centers in public commentary. C-weighting better captures lower frequencies.

Frequent aspects of data center infrastructure, such as cooling equipment, fans, and transformers, often produce lower frequency tones, which more readily traverse walls and windows and may be more prominent when there is less ambient noise, such as at night. A facility can produce steady, low-frequency sounds that are audible indoors at neighboring properties while staying within A-weighted thresholds.

Recent City measurements. A data center application in 2026 included two acoustical models that provide insight into the strengths and weaknesses of sound measurement practices. The applicant's representative and the city's used different software but relied on the same equipment, with data drawn under a common international standard. They predicted A-weighted decibels of 42 and 43, respectively, from the closest neighboring residential property line. Both predictions would be within the city threshold. [65]
The center’s chillers, which are typically the loudest outdoor equipment at a data center, were measured in a range that began at 63 hertz, so lower frequency noise was not captured by either model. [66] As alluded to above, establishing noise barriers is also less effective at lower frequency levels (lower frequency noise is better at penetrating barriers). The barrier specified for this project stops 30 dB at 125 Hz and 49 dB at 4,000 Hz, which is a large spread. A 10 dB increase is 10 times the amount of sound energy, and that registers as about twice as loud to the typical human ear. 30 dB passes through about eighty times more than 49 dB. In other words, the barrier in this case was eighty times more effective against high-frequency noise than against lower-frequency sounds.
These types of enclosures also require ventilation (called louvres), and those only block 6 dB at 63 hertz. The louvres therefore attenuate lower-frequency sounds less effectively than the solid panels attenuate higher-frequency sounds. [67]
What ongoing measurement found. In February 2026, a six-day sound study was performed continuously at the site. It recorded background noise levels ranging from 38.8 to 42.1 dB(A) during daytime hours and 39.4 to 43.8 dB(A) at night. The nighttime noise limit that applies is 6-11 dB higher, or up to about twice as loud, than the recorded noise level. [68] These limits serve as a ceiling on the frequencies tested and compliance with them is not synonymous with not causing a perceptible change in noise levels.
Noise level regulation elsewhere. Some jurisdictions have regulations in place that are based on frequency rather than solely on decibel levels. As previously noted, Weld County has the only C-weighted noise limit that we identified, at 65 dB(C). [69] Portland, OR, can require noise levels to be measured in octave bands and adds potential penalties for sounds within a single octave, which suggests humming, droning, or similar sound patterns. New York City, Branson, Missouri, and Illinois also address low-frequency noise as does Colorado’s oil and gas regulatory structure. [70] Finally, it is worth recalling the case of Chandler, Arizona, which measures noise levels relative to a baseline set before the project is initiated.
Supplemental noise regulation measures. In addition to the A-weighted limits for which the City already has an established threshold, it might consider C-weighted or other lower-frequency or tonal metrics. It might also consider requiring measurement before project initiation and ongoing monitoring after construction is complete, using the same standards and classes of equipment. No national C-weighted standard specific to data centers was identified, so any threshold would be locally set; Weld County’s 65 dB(C) limit is the only adopted example we found.
Backup Generation and Emergency Response
It is typical for large data centers to include significant back-up power generation. The Virginia legislature-based study referenced above found that these generators are run mostly for maintenance and testing, and that in Northern Virginia they accounted for less than 4 percent of regional nitrogen oxide emissions and 0.1 percent or less of regional carbon monoxide and particulate matter emissions. [71]
In Colorado, emergency power generators are subject to air emission restrictions and other construction regulations, which vary based on the size, anticipated emissions, and other factors. [72] Colorado Springs is not the permitting authority under the state’s air permitting program but there are several other mechanisms at its disposal to regulate these particular aspects of data center sites: siting, screening, setbacks, fuel storage, spill containment, fire code coordination, testing schedules, and emergency-response coordination, to name a few. [73]
Colorado law allows local governments to impose impact fees on new development to fund its share of public capital facilities, which could include added emergency-response capacity. The statute conditions that authority by requiring legislative adoption, general applicability to a broad class of uses, documentation justifying a correlation between the impact and the amount assessed, and a five-plus year lifetime for the facility in question. Fees cannot exceed amounts necessary to defray impacts directly stemming from the site and cannot be applied to unrelated capital deficiencies. Impact fees are also subject to the federal takings limits discussed below: an exaction must bear an essential nexus and rough proportionality to the development’s impact under Nollan and Dolan. [74]
One recent example indicates the need to ensure that these overlapping regulatory schemes are recognized in efforts to address public concerns. Generators at a City facility were to be tested for no more than 30 minutes, but a daytime test of up to 15 minutes would fall within the Code’s allowance for permissible increases. [75]
Water Use
Data center water demand is driven by the need for cooling. The options involve tradeoffs. One common approach is evaporative cooling, which requires less energy but more water. Dry cooling systems use very little water but usually much more electricity. Closed-loop liquid cooling recirculates its coolant and draws water mainly for makeup, so its consumption is lower still. Any reported water figure should therefore identify the cooling type before it is compared across sites. Additional indirect water use for other purposes, such as restrooms, landscaping, and other building functions, can be substantial and may exceed volumes used for cooling in some cases, depending on design, regional climate, efficiency, and other factors. [76] [76B]
Current concerns about water use may be exacerbated because Colorado Springs, like much of Colorado and the broader region, is experiencing an historic drought. This could be a rationale for the City to weigh water use more heavily when considering a comprehensive data center regulatory regime. If that is the case, it may build in a preference for systems with dry heat rejection, though added electrical demand will need to be considered. As noted above, the City could use its proven 11,000 gallons per MW standard for developing policy, but it will need to validate projected water consumption when it comes to considering specific data center sites.
Energy Demand and Impacts on Community Rates
To begin analysis of the City’s existing approach to regulating what it classifies as large load electricity-consuming sites, we refer to two Colorado-based benchmarks. The one adopted by the Platte River Power Authority (PRPA), which provides power service to its co-owner cities of Longmont, Fort Collins, Loveland, and Estes Park, is the first. The second is for-profit provider Xcel Energy’s proposal to apply a tariff to sites of 50 MW or more, which may decrease to 20 MW for new sites.
Provision Colorado Springs Utilities Platte River Xcel (proposed)
Applicability threshold 10 MW Large load policy 50 MW or more; may also apply to new 20-50 MW customers
Minimum contract term 10 years Long-term contract required 15 years
Minimum bill obligation 100% of contracted load for 10 years Take or pay policy, requiring a minimum purchase whether or not utilized Minimum bill at 80% of contracted demand
Collateral or deposit 36 months of minimum bills Down payment requirements Upfront deposit and study fees
Infrastructure cost Assigned to customer Assigned to customer Assigned to customer, including new generation and transmission
Approval authority City Council serving as Utilities Board Board of Directors Public Utilities Commission
Status Adopted Adopted Pending before PUC

On upfront payments, minimum required billing obligations, and term length, the City’s schedule for its 10 MW threshold is as or more protective than the PRPA and applies to sites 20 percent the size of those Xcel is proposing to capture with its policies.  

Our research did not uncover an example of a standby schedule, where a different rate is applied to energy furnished as a back-up to a site’s own independent electricity production. Such “behind the meter” arrangements may warrant distinct consideration.

On-Site Generation and Efficiencies
On-site generation is often suggested in response to concerns about power consumption and its impact on broader community rates. While it does not eliminate demand on shared power sources, it can reduce it meaningfully. Common sources such as fuel cells or gas turbines warrant emission and permitting considerations, however. Some developer proposals include small, modular reactors but we did not find any that have been licensed to operate at commercial scale in the United States. [77] Solar cells coupled with on-site storage are also often raised, though such facilities are typically too small to carry a data center’s full and continuous electrical load.[ii] [78]
Center-adopted efficiency measures may have a greater impact than on-site production.  Strategies known as direct-to-chip and immersion cooling allow for coolants to reach higher temperatures and generally use less energy than traditional air cooling. Just how much water use they reduce depends on local climate and the facility’s heat rejection system. When they are paired with dry coolers and closed-loop heat rejections, their impact on decreasing water use can be substantial. When paired with evaporative towers or waterside economizers, on-site water use would remain substantial. [79] A nearby thermal off-taker is required to capture waste heat from these methods. [80] Because the water and energy performance of these technologies depends on the configuration in which they are deployed, requiring disclosure and measured performance is more durable than specifying which technology a site must use. No source we reviewed projects that efficiency gains will eliminate water or electricity demand as policy concerns at the facility scales under discussion.

Fiscal Impact

This section addresses considerations the City could take into account for projecting and evaluating the impact of data centers on its budget and longer-term fiscal outlook. Additional City- and site-specific data would be required to generate valid projections.

Revenues.   A number of different sources of revenue may apply to data center facilities: (1) real property tax at the nonresidential rate; (2) business personal property tax on servers and equipment, which may be the largest portion of a site’s revenue contribution; (3) sales and use taxes on servers and construction materials, which the City can collect directly due to its home rule status; and (4) additional use tax on construction materials.

Costs. Expenses that subtract from net fiscal benefit can include facility-related costs borne by the City, additional emergency response capacity, new road and other infrastructure changes, and rate increases that are not captured or fully mitigated by the site’s rate agreement. If a facility receives a tax incentive, abatement, or other financial incentive, this also constitutes a direct cost or foregone revenue that belongs on this side of the ledger.

Available evidence. Virginia’s legislative research agency produced what is likely the most independent assessment of the fiscal impact of data centers yet available. It identified substantial revenues offset considerably by sales tax exemptions and potential future electricity-rate increases for other customers. [81] While the exact dollar figures are unique to the contexts that body evaluated, the methodology of fully accounting for revenues and expenses is a firm precedent to follow.
Inputs required to perform a valid accounting. These are the potential line items the City might include for a complete assessment of the fiscal impact of a data center site:
  • Facility size;
  • Assessed value of improvements;
  • Business-related personal property value;
  • Annual anticipated technology/equipment refresh value, including any other inventory expected to be refreshed annually that may generate sales tax revenue;
  • Applicable depreciation;
  • Abatements or other incentives;
  • Taxable construction expenses;
  • The City’s methodology for attributing service costs;
  • Analysis of the utility’s cost of service, which may be embedded in the existing large load facility schedule.
Stranded or Decommissioned Facilities
For designated large load sites, the contracts address the possibility of premature facility closure, such as minimum billable timeframes, down payments or collateral, etc. As we have frequently noted, however, the Electric Large Load safeguards do not apply to data centers whose loads remain below the tariff threshold.
Land use considerations are not currently addressed, regardless of electrical load. If a data center closes, there is a large building, power generators, and other equipment still to be dealt with. One example of addressing this is in Logan County, Colorado, which requires a bond for potential decommissioning that includes an engineer’s cost estimate that must be recertified every five years. [82] Practices in mining reclamation and renewable energy decommissioning could be informative. They apply a published formula rather than negotiate these terms on a project-by-project basis.

Community Investment

Municipalities across the country are pursuing community investment from data center developers that extends beyond anticipated tax revenue. Colorado law applies some restrictions on how the City may approach this aspect of data center policy, though it still has considerable leeway within those constraints.
The Three Sources of Municipal Authority
Regulatory. The City may impose conditions on approving new centers via its land use authority, but they must be predictable, broadly applicable, and adopted in advance of a new site application. [83] If the City demands a land easement or money from a particular applicant, Colorado law requires that the exaction be directly connected to and proportional with the site's impact, a difficult bar to clear. [84] The U.S. Supreme Court recently confirmed that these parameters apply whether conditions are adopted legislatively or administratively. [85]
Contractual. The above-referenced legal parameters do not preclude the City from embedding some community benefit commitments in contracts that extend beyond its broadly applicable defaults. It can extend vesting rights for the site, which protect it from subsequently adopted zoning standards, in exchange for specific obligations. [86] It can also negotiate an incentive payment or tax credit under a qualifying tax-incentive agreement, within some statutory limits. [87] These are lawful ways to embed developer commitments in the contracting phase and are likely more durable than unilaterally imposing them.
Proprietary. Because the City owns the relevant utilities and therefore is exempt from PUC rate regulation, it can establish utility service terms by tariff and contract. [88] These may include recovering the cost of infrastructure improvements, minimum billing amounts, posted collateral, and water service conditions that can be embedded in site-specific contracts.

Examples of Community Benefits

In surveying relevant jurisdictions, we found four categories of community benefit that data center sites were providing: (1) neighborhood investment; (2) developer funding of infrastructure improvements; (3) local hiring, training, and sourcing; and (4) commitments relating to resource use. These categories and some specific examples of each are included in the table below.

For facilities at or above the 10 MW threshold, the City is already positioned to capture items in the second category. While some of the items in the other categories could be obtained through project-specific negotiation, an approach that may prove more durable and support consistent administration, subject to the legal limits above, would be to select benefits that could be broadly imposed across sites in advance of unique applications.

Community Benefit Commitments Across Reviewed Jurisdictions
01

Neighborhood Investment

  • Parks
  • Trails
  • Open space
How obtained in jurisdictions reviewed
Case-by-case negotiation
02

Infrastructure Cost Recovery

  • Transmission
  • Substation
  • Water connections
  • Road connections
How obtained in jurisdictions reviewed
Published tariff, above threshold

Colorado Springs is already positioned here.

03

Workforce

  • Local hiring
  • Apprenticeships
  • Local procurement
How obtained in jurisdictions reviewed
Case-by-case negotiation
04

Resource Commitments

  • Cooling technology
  • Water reuse
  • Renewable energy
  • Waste heat capture
  • Noise mitigation
How obtained in jurisdictions reviewed
Case-by-case negotiation
How obtained in jurisdictions reviewed

Recommended approach

Convert categories 01, 03, and 04 to published standards applying above a defined threshold, adopted before a site application and before service commitments are made.

Oversight and Succession
A common failure of these types of commitments occurs when ownership of a facility site changes. Some practices that help mitigate this risk include: (1) applying obligations to the land rather than the occupant; (2) embedding change-of-control provisions that trigger review upon sale; (3) financial protections, like surety bonds or escrows, that are recoverable even in the event of bankruptcy; and (4) detailed and ongoing monitoring, reporting, and enforcement mechanisms.
Independent third-party review is well established outside the data center context. Federal energy regulation, state utility commissions, municipal finance law, and standard Colorado practice all use applicant-funded independent reviewers who the jurisdiction participates in selecting. [89] Applicant-funded technical review would require applicable City authority, adopted standards, and charges reasonably related to the review costs; the cited authorities do not establish that those conditions alone authorize every such requirement. [90]
Colorado law does not allow local governments to require a developer to negotiate unspecified benefits with the community as a condition of approval. Consistent with notations above, any preconditions of this nature must be based on formally adopted, broadly applicable mechanics. [91] In the Colorado context, a three-step strategy is sustainable and may be strategically advantageous: set initial requirements by ordinance, apply them uniformly, and negotiate anything beyond them through a development or incentive agreement that ties them to specific aspects of the project.

Consideration Process

Current Approach
Currently, data centers fall within an existing permitted industrial use, so the process for their approval is administrative. Under that construct, public notice must be given and there must be an opportunity for public comments to be received. Ultimately, the decision is made at the staff level and based on whether or not the site meets the existing standards.
While this process is efficient for the City and potential site developers, it gives an impression that there is not adequate opportunity for the public to influence the outcome of the decision. This concern, which appears with relative frequency in the public record, is compounded by the fact that the current process and standards are not designed for data centers, specifically. [92]
Pathway Options
Pathway for consideration What it produces Tradeoff
Administrative (current) Fast and predictable; notice and written comment are required, with appeal to the Planning Commission, but no hearing is automatic Limited public participation; no data center-specific criteria
Opportunity for conditional or special use permit above a MW threshold Hearing, criteria-based findings, ability to impose conditions or community benefits Slower; each decision reviewable in court
Substantive, data center standards without mandatory hearings Maintains predictability and addresses portion of public concern No forum for public participation so transparency concerns may persist
These options are not mutually exclusive. The most common approach among municipalities that have taken action on the issue was to adopt substantive standards and only require hearings for facilities that exceed a certain threshold, whether based on anticipated electricity demand, size, or other criteria the City chooses to define. Those two are examples rather than a closed list.
Importance of Building a Record
While adopting new standards or amending current ones is a legislative act of the City Council, after that the decisions on whether applications meet those criteria are quasi-judicial and can be contested based on the record generated by the review process. [93] Typically, the best practice for such quasi-judicial processes is to include reasonable notice, opportunities for public input, documented findings vis-à-vis established criteria, and a published record. 
We previously raised the cautionary case of Prince William County. There, a tranche of site approvals was invalidated due to failure to meet specified procedural standards, not because the facilities did not meet substantive criteria. Even if the injured parties had effective knowledge of the content of the process, the fact it did not follow the technical details led to its failure. [94]
For new applicant considerations that fall under the current structure, the UDC states that major modifications must be approved by the entity that was responsible for approving the original permit and by the same procedure. In current practice, the entity and “original” permit are identified based on the use entitlement that is being modified, not necessarily the first approval the property received. [95] Clarifying this nuance and documenting it in the UDC may mitigate potential vulnerability for future decisions.
Impact on Current Sites
Colorado law prohibits applying new regulatory changes to a qualifying vested site-specific development plan for a defined period of time, subject to statutory exceptions. [96] Therefore the timing of prior and pending applications will be an important factor in determining the immediate impact of any new measures the City adopts.
The City’s UDC may present ambiguity on this account. It describes each development plan as a “planning document only.” Approval of a plan, alone, does not grant a variance and it expires in six years unless a building permit is awarded or specified use commences. [97] We did not find a section of the Code that clarifies whether and when development plan approval might qualify for Colorado law protections from changes imposed via new regulations. That is a question for the City Attorney.
The Moratorium Question
As described above, four Colorado jurisdictions — Denver and Boulder, Jefferson, and Larimer Counties — have opted to impose moratoriums on new data center facilities while they consider new standards for that sector. Colorado courts have upheld reasonable, temporary development moratoriums adopted to study land use policy; the cited decision did not concern data centers. [98] State statute prevents moratoriums from applying to sites that have received vested rights.

Proposed Policy Options

This section outlines, via the chart below, some policy alternatives that the City might consider pursuing in its effort to implement a durable, evidence-based approach to considering data center applications and ongoing oversight of these sites.

Option Problem addressed Decisionmaker and instrument Timing Burden Evidence
Define “data center” in the Unified Development Code Without the defined term, clearly applicable standards cannot be applied to this category Council ordinance Near term Staff drafting; standard amendment process High
Reconcile the existing 10 MW large-load threshold with facility scale Electric Large Load safeguards do not apply below the tariff threshold Council as Utilities Board; ordinance for land use threshold Near term Analysis of local load data and weighing of development impacts High
Clarify basis for measuring compliance with noise code Current practice defines relevant cap by adjacent use Council ordinance Near term Low; drafting only Moderate
Codify water study threshold Operative rule exists only as utility practice Utilities Board tariff or rule Near term Low, once technical basis is confirmed Moderate
Require independent pre-approval ambient sound study Avoids arbitrary cutoffs when sites may not add substantial noise Council ordinance; applicant-funded Near term Applicant cost; staff oversight Moderate
Publish aggregate facility reporting No comprehensive City inventory was located Utilities and Planning, administrative Near term Staff time; security review High
Clarify major modification provision Current standard subject to varying interpretation Council ordinance Near term Low Moderate
Convene a City-run public session Public concerns about transparency Administrative Near term Staff time; public safety planning and staffing High
Adopt tiered size thresholds Same standards apply to all industrial users Council ordinance Medium term Threshold analysis Moderate
Add supplemental low-frequency metric A-weighted limit may not capture tonal content Council ordinance Medium term Acoustical consultant; enforcement protocol Moderate
Public hearing above a threshold No automatic public hearing even for larger facilities Council ordinance Medium term Longer review; litigation exposure Moderate
Require financial assurances for possibility of abandonment No such obligation exists Council ordinance Medium term Legal review; formula development Limited
Build a reusable model for assessing fiscal impact No transparent, replicable basis for assessing City Finance with County Assessor Medium term Analyst time Moderate
Adopt broadly-applicable community investment requirements Colorado law preempts ad hoc mandates Council ordinance Medium term Legal review; policy development Moderate

In terms of sequencing, defining the data center use category could precede or be adopted in conjunction with applying specific conditions or other regulations on their approval. The City has independent pathways and authority for amending the existing large-load threshold, clarifying nuances in how the existing noise standard is applied, adopting a threshold for mandating a water use study, and publishing a list of current sites.

In drafting an ordinance, the City could consider varying parameters based on facility design, function, and other characteristics, rather than applying one tranche of regulations to sites above a certain energy load threshold.

Options Examined but not Recommended

Moratorium. Because the City owns a host of relevant utilities and has access to data that peers lack, a moratorium would more likely be a source of delay that does not generate different substantive standards.

A fixed megawatt threshold. While Longmont adopted such a policy and it is relatively simple to administer, it cannot capture site-specific characteristics and impacts that truly speak to underlying concerns, such as noise, water use, and approval pathway.

Mandating specific technology. While the status of some technologies at present could support identification of the most effective means of addressing aspects of the approval and oversight continuum, that technology is rapidly evolving.

Public disclosure of facility-level data. While best practice is to put a heavy hand on the transparency side of the scale, publishing extensive details about scope and nature of energy load, water use, and infrastructure could pose serious security concerns. Aggregate counts and publicly posted ranges are sufficiently transparent without putting public safety at risk.

Limitations

We identified and evaluated community concerns drawn from the public record, which includes submitted comments, testimony, and local reporting, rather than pursuing individual interviews. Conducting a survey  would produce more reliable  data from such a large audience.

Water use data and analysis is drawn from four City facilities. Facilities that adopt different cooling strategies or deploy water in alternative ways will not likely conform to the patterns we observed.

As noted, we did not find any published analysis of the performance of any particular regulatory regime in meeting specified benchmarks such as environmental or fiscal impacts, public satisfaction with the approval process, etc.

Several technical standards relevant to the noise and cooling analysis are paywall-protected and could not be accessed. We did not generate any findings or recommendations based on them.

The report does not provide legal advice, and any option the City pursues should be reviewed by the City Attorney before adoption.